Portal and integration modernization
Musterwerk Antriebstechnik GmbH
Scope
- Stage 1: administrative access restricted, second factor, available patches applied
- Stage 2: monitored integration between the ERP standard interface and the portal, replacing the CSV exchange
- Stage 3: portal under version control, automated deployment, current password storage, supported hosting
- A written status for the customer's audit after each stage
Not included
- New portal features
- The ERP upgrade itself (coordinated, not delivered)
- Penetration testing, unless separately ordered
Team and roles
Schedule
Weeks count from the agreed start date.
Acceptance checks
- Administrative access no longer reachable from the internet
- Delivery dates in the portal match the ERP within the agreed delay for four weeks
- Every deployment automated and logged; old server decommissioned
- Each audit item has a closure note with evidence
Musterwerk's responsibilities
- Coordinate with the ERP partner for the interface
- Approve each stage before go-live
- Inform customers of the planned switch-over
Commercial basis
Milestone-based, one price per stage, set out in the proposal.
Risks
- The ERP partner's availability for the interface work
- Unknown customer integrations with the portal (knowledge gap)
Open decisions
- Hosting option for the portal
- Which data must move in near real time