Discovery · Project definition

Portal and integration modernization

Musterwerk Antriebstechnik GmbH

Situation
An audit finding and an end-of-life deadline
Access
Tier B
Prepared by
Aleph Engineering GmbH
Version
1.0, reviewed by a second engineer

Scope

  • Stage 1: administrative access restricted, second factor, available patches applied
  • Stage 2: monitored integration between the ERP standard interface and the portal, replacing the CSV exchange
  • Stage 3: portal under version control, automated deployment, current password storage, supported hosting
  • A written status for the customer's audit after each stage

Not included

  • New portal features
  • The ERP upgrade itself (coordinated, not delivered)
  • Penetration testing, unless separately ordered

Team and roles

Lead engineer
Accountable for the plan, the architecture decisions, and the audit status.
Engineer
Builds the integration and the deployment; every change reviewed by a second engineer.
Your side
Ms Roth approves each stage; Mr Wendt confirms what customers need to see; your ERP partner joins for the interface.

Schedule

Week 1
Stage 1: urgent exposure closed.
Weeks 2-7
Stage 2: new integration, run in parallel with the old one until results match.
Weeks 6-10
Stage 3: portal moved, old server switched off.

Weeks count from the agreed start date.

Acceptance checks

  • Administrative access no longer reachable from the internet
  • Delivery dates in the portal match the ERP within the agreed delay for four weeks
  • Every deployment automated and logged; old server decommissioned
  • Each audit item has a closure note with evidence

Musterwerk's responsibilities

  • Coordinate with the ERP partner for the interface
  • Approve each stage before go-live
  • Inform customers of the planned switch-over

Commercial basis

Milestone-based, one price per stage, set out in the proposal.

Risks

  • The ERP partner's availability for the interface work
  • Unknown customer integrations with the portal (knowledge gap)

Open decisions

  • Hosting option for the portal
  • Which data must move in near real time